Heavy Haul FAQ · Sourced from state DOTs

How Long Does an Oversize Permit Take?

Routine permits vs superloads, published lead times and how long a permit stays valid, state by state.

Last verified: against official state sources.

This is a summary, not legal advice, and permit rules change. Items marked verify with the state could not be confirmed from an official source. Confirm current conditions with the issuing agency, or let us handle it: every load we book is permitted and routed for you.

Short answer

A routine oversize permit is often issued the same day, and in states like Washington and North Dakota most can be self-issued online 24/7. Superloads take much longer: at least 10 business days in Nevada, up to 14 days in Utah, and typically 3 to 4 weeks for a Texas superheavy permit without an approved route.

Lead times

Permit Timing by State

StateRoutine permitsSuperloads and validityOfficial source
WashingtonMost routine permits self-issued online 24/7Superloads: WSDOT office onlyWSDOT: Commercial vehicle permits
North DakotaPermits not subject to approval available 24/7 onlineSingle trip valid for a one-way move within 5 daysNDHP: E-Permits
UtahSingle-trip oversize permit valid 96 hoursSuperloads processed business hours only; up to 14 daysUDOT: Oversize & Overweight Provisions
NevadaNDOT Carson City office or online (not ports of entry)Superloads: submit at least 10 business days aheadNDOT: Over Dimensional Vehicles
WyomingPorts of entry clear loads up to 18 ft wide / 160,000 lbOver 18 ft wide or high: at least 24 hours' notice; permits up to 4 daysWHP: Commercial Carrier
TexasTxPROS onlineSuperheavy: 3 to 4 weeks unless a route is already approvedTxDMV: Superheavy Single-Trip Permits
ColoradoCOOPR online; must be issued before entering ColoradoChapter 6 and superloads reviewed separately: verify with the state for timingCDOT: Permitting Information
MontanaeTRIPS online (since Dec 2025)Superloads may need route surveys and a travel plan: verify with the state for timingMDT 2026 Trucker's Handbook (PDF)
Oregon, Idaho, California, Arizona, New Mexico, South Dakota, Nebraska, Kansas, OklahomaOnline systems; published processing times not confirmedverify with the stateSee each state guide

Planning

What Actually Sets the Schedule

  • Permit validity is short. Utah single-trip permits run 96 hours, Wyoming up to 4 days, North Dakota 5 days. Book the truck and escorts before the permit, not after.
  • Every state on the route. A three-state move needs three permits, and the slowest state sets the schedule.
  • Get it before you enter. Colorado and Utah (except at three ports) require the permit before the load enters the state.

By state

State-by-State Detail

State guides: Oregon · Washington · Idaho · California · Nevada · Arizona · Utah · Montana · Wyoming · Colorado · New Mexico · Texas · North Dakota · South Dakota · Nebraska · Kansas · Oklahoma. Permit detail: Oregon · Washington · Idaho · California · Nevada · Arizona · Utah · Montana · Wyoming · Colorado · New Mexico · Texas · North Dakota · South Dakota · Nebraska · Kansas · Oklahoma.

Have a specific load? Request a quote or run it through the permit checker. Every load we book is permitted, escorted and routed for you.

Questions we get

Frequently Asked

How long does it take to get an oversize permit?

Routine permits are often same-day, and Washington and North Dakota let most be self-issued online 24/7. Superloads take days to weeks.

How far ahead should I apply for a superload permit?

At least 10 business days in Nevada, up to 14 days in Utah, and about 3 to 4 weeks for a Texas superheavy permit without an approved route.

How long is an oversize permit valid?

It varies: 96 hours for a Utah single-trip permit, up to 4 days in Wyoming, and 5 days in North Dakota.

Can I get an oversize permit at a port of entry?

In Wyoming, yes, for loads up to 18 ft wide, 17 ft high, 120 ft and 160,000 lb. Nevada and Washington ports of entry do not issue them.

Do I need a permit for every state on the route?

Yes. Each state issues its own permit, and county or city roads may need local permits too.

Keep reading

Related

Rather not sort through the rules?

Send the dimensions and lane. We handle permits, escorts and routing on CRST's network. Call (310) 989-6530.

Request a Quote

Let's Move Something

Got a Load?

Tell me what it is and where it needs to go. I will get back to you the same day, with CRST's asset-based network behind every quote.

Call or Email Direct

No portals, no phone trees. You get the person who books your freight.

Same-day response on every quote request. If a load is sitting, call. That is what the phone is for.

Or Drop Me the Details

Tell me what you are moving and I will respond same day.

Goes straight to my inbox, and I respond same day. Or just call (310) 989-6530.